Question 101
Multiple Choice
It is common to progressively elaborate the network diagram
Question 102
Multiple Choice
The responsibility assignment matrix may use a P to designate ____ responsibility and an S to indicate ____ responsibility for a specific work item.
Question 103
Multiple Choice
The ____ shows all the individuals associated with each work item in the work breakdown structure, as well as all the work items associated with each individual.
Question 104
Multiple Choice
An activity in a network diagram cannot start until
Question 105
Multiple Choice
Standard subnetworks should be developed for those portions of projects for which
Question 106
Multiple Choice
A network diagram is a tool for arranging the specific activities in the ____ and defining their ____.
Question 107
Multiple Choice
The ____ is a roadmap that displays how all the specific activities fit together to accomplish the project work scope.
Question 108
Multiple Choice
To draw a ____, start by drawing the activities in boxes in their logical sequence and connecting them with arrows to show the required dependent relationships, as the project should be performed from start to completion.
Question 109
Multiple Choice
____ contains a small number of higher-level activities rather than a large number of detailed activities.
Question 110
Multiple Choice
Each activity in a network diagram is represented by a box in the ____, and the ____ of the activity is written within the box.
Question 111
Multiple Choice
Activities should ____ the time intervals at which actual project progress will be reviewed and compared to planned progress.
Question 112
Multiple Choice
Arrows linking the activity boxes in a network diagram show the ____ of the dependent relationship.
Question 113
Multiple Choice
In preparing a network diagram, drawing activities in a ____ is not acceptable because it portrays a path of activities that perpetually repeats itself.
Question 114
Multiple Choice
Designating ____ as having primary responsibility can cause confusion and increase the risk that some work will "fall through the cracks," because each may assume that the other is going to do it.