A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days) of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the probability that the project takes more than 34 days?
A) 0.788
B) 0.212
C) 0.945
D) 0.055
Correct Answer:
Verified
Q83: A gentleman farmer maniacally works on
Q84: Use the values in the table to
Q86: The PERT technique assumes that durations are
Q87: Q89: The BEST candidate activities for shortening the Q89: What is the float start time Q90: Use the information in the table to Q91: Use the values in the table Q93: A project's duration can be reduced by: Q93:
A)Shortening
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents