Multiple Choice
What is the float start time for Activity C given the activity times and precedence requirements shown in the table?
A) 1
B) 2
C) 3
D) 4
Correct Answer:
Verified
Related Questions
Q84: Use the values in the table to
Q85: One approach to reducing project length would
Q86: The PERT technique assumes that durations are
Q87: Q88: A gentleman farmer maniacally works on Q89: The BEST candidate activities for shortening the Q90: Use the information in the table to Q91: Use the values in the table Q93: A project's duration can be reduced by: Q93:
A)Shortening
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents