Solved

An Assumption of Three-Activity-Time CPM Analysis Is That the Activity

Question 81

Multiple Choice

An assumption of three-activity-time CPM analysis is that the activity time estimates conform to the beta distribution.Which of the following is a valid criticism of this assumption?


A) Project activities cannot always be networked
B) Project control doesn't focus enough on the critical path
C) Obtaining three valid time estimates to put into the formula is difficult
D) Beta distributions do not occur naturally
E) None of the above

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents