If the Pessimistic Duration of an Activity Is 10 and the Optimistic

Question 80

Multiple Choice

If the pessimistic duration of an activity is 10 and the optimistic duration is 4,what is the variance for the activity time when using CPM analysis?


A) 1
B) 2.333
C) 4.777
D) 10.4
E) 12