Which of the following is an assumption made in using CPM analysis?
A) Project activities flow together without distinct boundaries
B) Project activity times can be estimated accurately and do not vary
C) Project management should focus on crashing activities
D) There is never a work stoppage in any activity until it is complete
E) There are no learning curve effects in setting activity time
Correct Answer:
Verified
Q63: In CPM analysis, it is generally expected
Q76: Describe how CPM handles the trade-offs between
Q79: A company must perform a maintenance
Q80: If the pessimistic duration of an activity
Q81: An assumption of three-activity-time CPM analysis is
Q82: Below are the data for a Time-Cost
Q85: Below are the data for a
Q86: If the pessimistic duration of an activity
Q88: Below are the data for a
Q89: You have collected the data for
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents