The manufacturing cycle efficiency for Olsen Inc. when the processing time is five hours and inspection, waiting, and move time are two hours each is (rounded) :
A) 0.40.
B) 0.45.
C) 0.83.
D) 1.00.
E) 2.50.
Correct Answer:
Verified