Multiple Choice

Scott has just been given a project that has a specific completion date.After a discussion with top management he finds that while the date is important the cost is more important and a slip in delivery would be acceptable if required to meet the cost targets.The completion date is best classified as


A) Constrained.
B) Reduced.
C) Accepted.
D) Limited.
E) Optional.