Jose is looking at a document that outlines the specific deliverables and sub-deliverables required to complete the writing of a technical support manual.He is most likely viewing the
A) Responsibility matrix.
B) Organization breakdown structure.
C) Work breakdown structure.
D) Priority matrix.
E) Work package.
Correct Answer:
Verified