All resource leveling techniques involve
A) Delaying noncritical activities
B) Delaying critical activities
C) Using negative slack
D) Both A and C are correct
E) A, B, and C are all correct
Correct Answer:
Verified
Q4: Delaying noncritical activities to lower peak demand