Sam is trying to order the concrete needed to continue his project.However, the supplier won't be able to deliver it until next week.This is an example of a _______ constraint.
A) Working capital
B) People
C) Equipment
D) Information
E) Materials
Correct Answer:
Verified
Q7: If resources are not adequate to meet
Q8: In reviewing the status of her project
Q9: All resource leveling techniques involve
A)Delaying noncritical activities
B)Delaying
Q11: The most widely used approach to apply
Q12: Which of the following is a potential
Q14: Regina's boss has told her that her
Q15: In a resource-constrained project, which of the
Q16: A special truck that George needs on
Q17: When developing a new software package, the
Q18: All of the following are kinds of