In earned value management,schedule variance is defined as:
A) The difference between the earned value and the actual cost.
B) The difference between the earned value and the planned value.
C) The difference between the actual cost and the planned value.
D) The difference between the cost and schedule performance indices multiplied by the budgeted cost at completion.
Correct Answer:
Verified
Q41: Use the earned value table to
Q42: Duration (weeks) Q43: At the end of week 10,this Q44: The first step in earned value management Q45: The budget variance is calculated as: Q47: Use the data to calculate the Q48: Use the data to calculate the Q49: In earned value management analysis,the cumulative amount Q50: The project baseline is established by combining Q51: Use the data to calculate the
A)Earned value
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents