Duration (Weeks) -At the End of Week 25,this Project Has Cost $79,000

Question 42

Multiple Choice

Duration (weeks)
510152025%Cormp Conceptual desiern 106100% Craphics desigrl 1264100% Copyright 456100% Barmples 4270% Toolirg 69450% Production 261420% Total 1018222624 Currulative 10285076100\begin{array} { | l | l | l | l | l | l | l | } \hline & 5 & 10 & 15 & 20 & 25 &\%\mathrm { Cormp } \\\hline \text { Conceptual desiern } & 10 & 6 & & & & 100 \% \\\hline \text { Craphics desigrl } & & 12 & 6 & 4 & & 100 \% \\\hline \text { Copyright } & & & 4 & 5 & 6 & 100 \% \\\hline \text { Barmples } & & & 4 & 2 & & 70 \% \\\hline \text { Toolirg } & & & 6 & 9 & 4 & 50 \% \\\hline \text { Production } & & & 2 & 6 & 14 & 20 \% \\\hline \text { Total } & 10 & 18 & 22 & 26 & 24 & \\\hline \text { Currulative } & 10 & 28 & 50 & 76 & 100 & \\\hline\end{array}
-At the end of week 25,this project has cost $79,000 and has an earned value as indicated in the table.Use the data to calculate the cost performance index for the project.All amounts are in thousands of dollars.


A) 1.11
B) 0.82
C) 0.94
D) 0.90

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents