Use the data to calculate the schedule performance index for the project for the end of week 20.The earned value as of the end of week 20 is indicated in the table.All amounts are in thousands of dollars. Duration (weeks)
A) 1.14
B) 0.88
C) 0.94
D) 0.81
Correct Answer:
Verified
Q46: In earned value management,schedule variance is defined
Q47: Use the data to calculate the
Q48: Use the data to calculate the
Q49: In earned value management analysis,the cumulative amount
Q50: The project baseline is established by combining
Q52: Use the earned value table to
Q53: Use the earned value table for
Q54: A project manager can calculate the projected
Q55: Use the earned value table (all
Q56: Use the data to calculate the