Use the Earned Value Table for Project Makeready to Determine
Question 53
Question 53
Multiple Choice
Use the earned value table for Project Makeready to determine the earned value at week 49. Activity Install fixtures Refinish floors Replace doors Complete tiling Install back door Landscaping Monthly Plan Monthly Act 7325325550142505508005502185350435550282751,2001,4751,100355658751,4401,65042225200425550493503501,100 Plan 5756356251,7651,1005505,250%/1 Complete 100%100%100%80%70%25%
A) $4,950 B) $6,050 C) $4,155 D) $5,250
Correct Answer:
Verified
Unlock this answer now Get Access to more Verified Answers free of charge