Question 21
Multiple Choice
Which action involves defining and documenting the features and functions of the products produced during the project as well as the processes used for creating them?
Question 22
Multiple Choice
Which process involves generating ideas by comparing specific project practices or product characteristics to those of other projects or products inside or outside the performing organization?
Question 23
Multiple Choice
Which term describes a product produced as part of a project?
Question 24
Multiple Choice
Which task is at the lowest level of the WBS?
Question 25
Multiple Choice
Which output documents how project needs will be analyzed, documented, and managed?
Question 26
Multiple Choice
Creating the WBS is a subprocess associated with which process in project scope management?
Question 27
True/False
The format of the WBS dictionary is essentially the same for all projects.
Question 28
Multiple Choice
Which approach for constructing a WBS starts with the largest items of the project and breaks them into subordinate items?
Question 29
True/False
Scope creep if not managed well can lead to the failure of information technology projects.
Question 30
Multiple Choice
Which action involves normalizing acceptance of the project deliverables and during this phase the key project stakeholders, such as the customer and sponsor for the project, inspect and then formally accept the deliverables?