What is a schedule variance?
A) The budgeted cost of work performed during a specific time period (BCWP)
B) The budgeted cost of work scheduled during a specific time period (BCWS)
C) The difference between the budged cost of work performed and the budget cost of work scheduled for a specific time period (BCWP-BCWS)
D) The amount of time by which a project is behind schedule when no slack exists in the schedule budget
E) The difference between the money spent and the money projected to be spent on a project
Correct Answer:
Verified
Q52: In deciding on performance measures, organizations need
Q53: Because it is often very difficult and
Q54: As organizations have moved to more project-based
Q55: The global financial crisis that began in
Q56: Proxy measures of outcomes are used
A)To allow
Q58: Which project management tool shows the flow
Q59: Which project management tool identifies who is
Q60: Project managers are tasked with achieving project
Q61: One of the benefits of aligning compensation
Q62: In recent years, the term "compliance" has
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents