Cost Variance (CV) = Earned Value - ___________.
A) Budget at Completion (BAC)
B) Budgeted cost of remaining work (BCRW)
C) Schedule Variance (SV)
D) Actual Cost (AC)
E) None of these
Correct Answer:
Verified
Q20: As a project manager, you would be
Q21: Schedule Variance (SV) is _
A) how much
Q22: Barring a change in project scope and
Q23: The cost incurred for completing a scheduled
Q24: A _ is a formal or informal
Q26: A _ shows how the scope, features
Q27: The metric that provides an estimate of
Q28: The total planned cost of the project
Q29: Budget At Completion (BAC) is _
A) how
Q30: EV-AC =
A) Cost performance index (CPI)
B) Scheduled
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents