Barring a change in project scope and given a Schedule Performance Index (SPI) that is greater than 1, the most reasonable inference to draw is that:
A) The project will likely finish earlier than planned.
B) The project will likely finish later than planned.
C) The project will likely cost more than planned.
D) The project will likely cost less than planned.
E) The project will likely be on time and on budget.
Correct Answer:
Verified
Q17: A project metric should be obtained from
Q18: Planned value (PV) is the planned or
Q19: The Expected Time Complete (ETC) provides an
Q20: As a project manager, you would be
Q21: Schedule Variance (SV) is _
A) how much
Q23: The cost incurred for completing a scheduled
Q24: A _ is a formal or informal
Q25: Cost Variance (CV) = Earned Value -
Q26: A _ shows how the scope, features
Q27: The metric that provides an estimate of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents