The total planned cost of the project is computed before the project work begins. This metric is called the:
A) Planned Value (PV)
B) Budget At Completion (BAC)
C) Actual Cost (AC)
D) Expected Time Complete (ETC)
E) Estimate at Completion (EAC)
Correct Answer:
Verified
Q23: The cost incurred for completing a scheduled
Q24: A _ is a formal or informal
Q25: Cost Variance (CV) = Earned Value -
Q26: A _ shows how the scope, features
Q27: The metric that provides an estimate of
Q29: Budget At Completion (BAC) is _
A) how
Q30: EV-AC =
A) Cost performance index (CPI)
B) Scheduled
Q31: If you hired a consulting firm to
Q32: The budgeted cost of work scheduled for
Q33: Cost Variance (CV) is _
A) how much
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents