
Consider the following work breakdown structure:
What is the probability that the critical path for this project will be completed within 210 days?
A) 0.5000
B) 0.8413
C) 0.9544
D) 0.9772
E) 0.9987
Correct Answer:
Verified
Q74: Which of the following are advantages of
Q78: The basis for use of the beta
Q80: In the probabilistic approach to project network
Q81: Consider the following work breakdown structure:
Q82: A project is represented by the following
Q84: Consider the following work breakdown structure:
Q85: Consider the following work breakdown structure:
Q86: Consider the following work breakdown structure:
Q87: Consider the following work breakdown structure:
Q88: A project is represented by the following
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents