
Consider the following work breakdown structure:
What is the estimated standard deviation in the time for activity E?
A) 1 days
B) 2 days
C) 3 days
D) 4 days
E) 5 days
Correct Answer:
Verified
Q82: A project is represented by the following
Q83: Consider the following work breakdown structure:
Q84: Consider the following work breakdown structure:
Q85: Consider the following work breakdown structure:
Q86: Consider the following work breakdown structure:
Q88: A project is represented by the following
Q89: Consider the following work breakdown structure:
Q90: Consider the following work breakdown structure:
Q91: Consider the following work breakdown structure:
Q92: Consider the following work breakdown structure:
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents