Assume that the standard cost to make one finished unit includes 1 hour of direct labor at $4 per hour. During March, 11,000 direct labor-hours were worked, 5,250 units of product were manufactured, and total direct labor cost was $40,000.
What is the labor rate variance for April?
A) $2,000 (U)
B) $2,000 (F)
C) $4,000 (U)
D) $4,000 (F)
Correct Answer:
Verified
Q20: Standard costs:
A) Indicate what it should cost
Q21: A flexible budget variance for a manufacturing
Q22: Budgets based on the actual level of
Q23: By using time and motion studies, it
Q24: Assume that the standard cost to make
Q26: The difference between an actual cost number
Q27: The objective of standard cost variance analysis
Q28: Which of the following descriptions best defines
Q29: Which of these factors is not a
Q30: Which of the following factors describes a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents