Which statement is incorrect:
A) Unlike the critical path, the critical chain ensures stability on the project.
B) The critical chain is likely to reduce project duration.
C) The critical chain is, in general, longer than the critical path.
D) The critical chain results in a high probability of finishing the project on the promised date.
E) Unlike the critical path, the critical chain ensures that a resource is scheduled to do only one activity at any specific time.
Correct Answer:
Verified
Q3: To find the shortest possible project duration
Q4: Which statement is correct: In the CPM,
Q5: If a = 3, m = 5,
Q6: If the project completion has a distribution
Q7: Which statement is correct. The critical chain
Q9: A project cannot have more than one
Q10: Contingencies should be built in at the
Q11: The following type of buffer does not
Q12: The following buffer enables the project manager
Q13: Resource buffers are always placed:
A) on the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents