Which statement is correct. The critical chain method:
A) helps planners to estimate the duration of activities more accurately.
B) stresses that, in order to finish the project on the project deadline (due date) , all critical activities must be finished by their individual deadlines (due dates) .
C) forces a person working on an activity to commit to when he/she will finish the work.
D) ensures that sufficient contingency reserve is built into the schedule of each individual activity.
E) None of the above is correct.
Correct Answer:
Verified
Q2: When there are multiple critical paths and
Q3: To find the shortest possible project duration
Q4: Which statement is correct: In the CPM,
Q5: If a = 3, m = 5,
Q6: If the project completion has a distribution
Q8: Which statement is incorrect:
A) Unlike the critical
Q9: A project cannot have more than one
Q10: Contingencies should be built in at the
Q11: The following type of buffer does not
Q12: The following buffer enables the project manager
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents