Solved

Which Statement Is Correct. the Critical Chain Method

Question 7

Multiple Choice

Which statement is correct. The critical chain method:


A) helps planners to estimate the duration of activities more accurately.
B) stresses that, in order to finish the project on the project deadline (due date) , all critical activities must be finished by their individual deadlines (due dates) .
C) forces a person working on an activity to commit to when he/she will finish the work.
D) ensures that sufficient contingency reserve is built into the schedule of each individual activity.
E) None of the above is correct.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents