To find the shortest possible project duration for the least cost:
A) crash all activities on the critical path (CP) , then relax all non-CP activities
B) crash all activities not on the CP, then relax all critical activities
C) crash all activities in the project, then relax those not on the CP
D) crash all activities in the project, then relax those on the critical path
Correct Answer:
Verified
Q1: To reduce the duration of a project
Q2: When there are multiple critical paths and
Q4: Which statement is correct: In the CPM,
Q5: If a = 3, m = 5,
Q6: If the project completion has a distribution
Q7: Which statement is correct. The critical chain
Q8: Which statement is incorrect:
A) Unlike the critical
Q9: A project cannot have more than one
Q10: Contingencies should be built in at the
Q11: The following type of buffer does not
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents