Solved

To Find the Shortest Possible Project Duration for the Least

Question 3

Multiple Choice

To find the shortest possible project duration for the least cost:


A) crash all activities on the critical path (CP) , then relax all non-CP activities
B) crash all activities not on the CP, then relax all critical activities
C) crash all activities in the project, then relax those not on the CP
D) crash all activities in the project, then relax those on the critical path

Correct Answer:

verifed

Verified

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents