Question 81
Multiple Choice
The ________ is a sequence of activities that determine the earliest date by which a project can be completed.
Question 82
Multiple Choice
A ________ shows the tasks, dates, and dependencies for the tasks of a project.
Question 83
Multiple Choice
The ________ phase of the systems development life cycle (SDLC) involves determining hardware and program specifications, designing the database and procedures, and creating job definitions.
Question 84
Multiple Choice
In systems development, documents, designs, prototypes, data models, database designs, and working data entry screens are examples of ________.
Question 85
Multiple Choice
Organizational feasibility concerns ________.
Question 86
Multiple Choice
Once the project's goals and scope have been defined, the next step in the system definition phase of the systems development life cycle (SDLC) is to ________.
Question 87
Multiple Choice
In the system implementation phase of the systems development life cycle (SDLC) , with ________ installation, the new system runs alongside the old one until it has been tested and is fully operational.
Question 88
Multiple Choice
In the system definition phase of the systems development life cycle (SDLC) , the first major task for an assembled project team is to ________.
Question 89
Multiple Choice
In the system implementation phase of the systems development life cycle (SDLC) , with ________ installation, the organization implements the entire new system/business processes on a limited portion of the business.