In the system definition phase of the systems development life cycle (SDLC) , the first major task for an assembled project team is to ________.
A) design system components
B) assess the project's feasibility
C) plan the project
D) define system goals and scope
Correct Answer:
Verified
Q43: The _ phase of the systems development