Which of the following is not a way to reduce the costs of activities:
A) Reduce the scope or requirements
B) Substitute less expensive materials.
C) Assign a person with less expertise or less experience to perform or help with the activity.
D) Increase productivity through improved methods or technology.
Correct Answer:
Verified
Q41: A method for calculating the forecasted cost
Q59: The is the amount that was budgeted
Q66: When evaluating work packages that have a
Q67: Calculate the forecasted cost at completion if
Q68: involves the following: analysing cost performance to
Q71: Managing cash flow involves making sure that
Q72: The contractor's outflow of cash can be
Q73: The contractor might try to negotiate payment
Q78: When evaluating work packages that have a
Q80: It's crucial that cost variances and inefficiencies
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents