Calculate the forecasted cost at completion if the cumulative actual cost is R100 000 and the re-estimate of remaining work to be performed is R50 000.
A) FCAC = R50 000
B) FCAC = R150 000
C) FCAC = 2
D) FCAC = 0.5
Correct Answer: