The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Table 9.3
-Using Table 9.3, the probability that the project will take longer than 33 weeks to complete is approximately
A) 0.19.
B) 0.32.
C) 0.68.
D) 0.81.
Correct Answer:
Verified
Q55: For an activity-on-node (AON)network,
A)arrows represent activities and
Q74: The estimated mean time for an activity
Q79: A project consists of the following four
Q81: The following table of probabilistic time estimates
Q82: The following table of probabilistic time estimates
Q83: The subjective estimate of the activity time
Q85: The following table of probabilistic time estimates
Q87: Which of the following statements is generally
Q88: The following table of probabilistic time estimates
Q89: Smartsheet is an online application which can
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents