The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Table 9.3
-Using Table 9.3, the earliest finish time for activity C is
A) 5.00 weeks.
B) 8.17 weeks.
C) 9.50 weeks.
D) 12.67 weeks.
Correct Answer:
Verified
Q49: A project consists of the following activities:
Q55: For an activity-on-node (AON)network,
A)arrows represent activities and
Q73: A project consists of the following activities:
Q74: The estimated mean time for an activity
Q78: A project consists of the following four
Q79: A project consists of the following four
Q82: The following table of probabilistic time estimates
Q83: The subjective estimate of the activity time
Q84: The following table of probabilistic time estimates
Q85: The following table of probabilistic time estimates
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents