The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Table 9.3
-Using Table 9.3, the earliest start (ES) time for activity D is
A) 8.17 weeks.
B) 12.67 weeks.
C) 18.33 weeks.
D) 21.67 weeks.
Correct Answer:
Verified
Q53: The estimated variance for an activity with
Q74: The estimated mean time for an activity
Q78: The estimated mean time for an activity
Q83: The subjective estimate of the activity time
Q84: The following table of probabilistic time estimates
Q85: The following table of probabilistic time estimates
Q87: Which of the following statements is generally
Q89: Smartsheet is an online application which can
Q90: The following table of probabilistic time estimates
Q93: Crashing is used to
A) increase project completion
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents