The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Table 9.3
- Using Table 9.3, the expected time to complete activity A is
A) 5.00 weeks.
B) 7.33 weeks.
C) 7.67 weeks.
D) 8.00 weeks.
Correct Answer:
Verified
Q53: The estimated variance for an activity with
Q74: The estimated mean time for an activity
Q78: The estimated mean time for an activity
Q85: The following table of probabilistic time estimates
Q87: Which of the following statements is generally
Q88: The following table of probabilistic time estimates
Q89: Smartsheet is an online application which can
Q93: Crashing is used to
A) increase project completion
Q94: The following table of probabilistic time estimates
Q95: The following table of probabilistic time estimates
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents