The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Table 9.3
-Using Table 9.3, how much slack is associated with activity C?
A) 0 weeks.
B) 4.50 weeks.
C) 12.67 weeks.
D) 31.00 weeks.
Correct Answer:
Verified
Q53: The estimated variance for an activity with