A negative CV indicates the project is currently ________ budget.
A) over
B) under
C) on track with
D) ahead of
E) behind
Correct Answer:
Verified
Q67: The _ variance is the difference between
Q68: Baseline project budgets are derived from time-phasing
Q69: A project can have a negative schedule
Q70: A Cost / Schedule graph can be
Q71: Conditions or scope can change during execution,
Q73: When someone familiar with each task estimates
Q74: The value that tells you how much
Q75: Which of the following is not one
Q76: The _ variance is the difference between
Q77: Taking action in the four steps for