When someone familiar with each task estimates what percent of the task has been completed or how much of the task remains, they are creating a method for assigning costs to the baseline called the ____________ rule.
A) estimated completion
B) estimated cost
C) percent complete
D) estimation
E) estimation method
Correct Answer:
Verified