A project can have a negative schedule variance and still be ahead of schedule when
A) all budget targets have been achieved.
B) earned value exceeds planned value.
C) progress on the critical path is faster than non-critical path tasks.
D) actual cost exceeds earned value.
E) None of these alternatives is correct.
Correct Answer:
Verified
Q64: The indicator that tells you the planned
Q65: The _ rule assumes credit is earned
Q66: When reviewing the cost variance on a
Q67: The _ variance is the difference between
Q68: Baseline project budgets are derived from time-phasing
Q70: A Cost / Schedule graph can be
Q71: Conditions or scope can change during execution,
Q72: A negative CV indicates the project is
Q73: When someone familiar with each task estimates
Q74: The value that tells you how much
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents