Why is it necessary to have a time-phased budget baseline?
A) It allows proper resource allocation.
B) It shows how much work was accomplished for the money spent.
C) It reduces schedule slippage when scheduling multiproject resources.
D) It is not necessary to have a time-phased budget baseline.
E) It reduces fluctuations in cash flow during the project.
Correct Answer:
Verified
Q39: Which of the following is NOT a
Q40: If resources are truly limited and activity
Q41: Technical constraints have been carefully considered when
Q42: A project budget report is showing our
Q43: Splitting an activity can result in all
Q45: This is used to compare the cost
Q46: When there are not enough people, money,
Q47: In a resource-constrained project the second priority
Q48: Resource leveling or smoothing can have all
Q49: When a company will reduce the number
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents