Technical constraints have been carefully considered when developing a project network. Which of the following is true at this point?
A) Resources have been assigned to each activity so they are adequate to complete the project on time.
B) Technical dependencies between activities are known.
C) The project completion date can be established.
D) The project is ready to be implemented.
E) All of these are true statements once technical constraints have been established.
Correct Answer:
Verified
Q36: Most of the scheduling methods available today
Q37: Project managers should always assign the best
Q38: Project management software is important because it
Q39: Which of the following is NOT a
Q40: If resources are truly limited and activity
Q42: A project budget report is showing our
Q43: Splitting an activity can result in all
Q44: Why is it necessary to have a
Q45: This is used to compare the cost
Q46: When there are not enough people, money,
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents