Resource leveling or smoothing can have all the following results on a project EXCEPT
A) lower peak resource demand.
B) reduced resource need over the life of the project.
C) reduced fluctuations in resource demand.
D) a longer project duration.
E) a more sensitive network.
Correct Answer:
Verified