These are all guidelines a project manager should consider when assigning project work EXCEPT
A) select people with compatible work habits and personalities.
B) always assign the best people to the most difficult tasks.
C) when possible, team veterans up with new hires.
D) select individuals with skillsets that complement each other.
E) have people work together early so that they can become familiar with each other.
Correct Answer:
Verified
Q46: When there are not enough people, money,
Q47: In a resource-constrained project the second priority
Q48: Resource leveling or smoothing can have all
Q49: When a company will reduce the number
Q50: When leveling schedules to overcome resource constraints,
Q52: Which of the following is NOT one
Q53: In a resource-constrained project, which of the
Q54: In a resource-constrained project the third priority
Q55: A project scheduler is working on a
Q56: A project leader has realized that two
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents