Because direct costs are assumed to be developed from "normal" methods and in a "normal" amount of time, any reduction in activity time should add to the costs of the activity.
Correct Answer:
Verified
Q7: When reducing project duration, there will always
Q8: Brooks' law states that adding manpower to
Q9: Crashing can negatively impact the morale and
Q10: The higher the cost slope of an
Q11: Crashing frequently results in over allocation of
Q13: If indirect costs are a significant percentage
Q14: Shortening an activity's duration is termed crashing.
Q15: The total cost for each time unit
Q16: Crashing a more expensive activity may be
Q17: Direct costs are so named because they
Unlock this Answer For Free Now!