The AON diagram shown represents a project. Normal and crash times, and the associated costs, are shown for each activity in the accompanying table. The normal completion time for the project is 130 weeks. If it is worth $10 000 a week to reduce the project duration, what is the shortest economical crash time?
A) There is no economical way to reduce completion time.
B) 10 weeks
C) 15 weeks
D) 20 weeks
E) 25 weeks
Correct Answer:
Verified
Q20: "CPM" stands for
A)Critical Path Method.
B)Company Profit Maximization.
C)Competitive
Q22: A feasibility study is associated with the
Q23: Explain how and when a project's risk
Q24: When resources such as overtime, extra equipment,
Q26: At what stage of a project's lifecycle
Q27: The AON diagram shown represents a project.
Q28: A new bridge project passed the feasibility
Q29: What are the five stages of a
Q30: A construction company has just started building
Q118: What is a project charter?
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents