When resources such as overtime, extra equipment, and additional staff result in higher costs, what should a project manager do?
A) Hire additional staff and acquire additional resources.
B) Terminate the project.
C) Make a tradeoff between the extra costs associated with crashing and the benefits of a reduced project completion time.
D) Look for a new sponsor of the project.
E) Delay the project until economic conditions change.
Correct Answer:
Verified
Q19: The nature and scope of a project
Q20: "CPM" stands for
A)Critical Path Method.
B)Company Profit Maximization.
C)Competitive
Q22: A feasibility study is associated with the
Q23: Explain how and when a project's risk
Q25: The AON diagram shown represents a project.
Q26: At what stage of a project's lifecycle
Q27: The AON diagram shown represents a project.
Q28: A new bridge project passed the feasibility
Q29: What are the five stages of a
Q118: What is a project charter?
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents