A construction company has just started building a new house. It was estimated that the project will take 12 months. However, the owner of the land asked the company to complete it in 10 months. What should the construction company do to accommodate the owner's request?
A) To deliver the project on time, one or several project activities should be crashed.
B) To deliver the project on time, the company should hire extra workers.
C) To deliver the project on time, the construction company should work overtime.
D) To deliver the project on time, the construction company should look for a new technology.
E) To deliver the project on time, the construction company should change the project.
Correct Answer:
Verified
Q25: The AON diagram shown represents a project.
Q26: At what stage of a project's lifecycle
Q27: The AON diagram shown represents a project.
Q28: A new bridge project passed the feasibility
Q29: What are the five stages of a
Q31: The AON diagram shown represents a project.
Q32: Suppose that a feasibility study done for
Q33: As a rule, each project includes a
Q34: A 5-year project requires $10 million in
Q35: Suppose that the crash cost is $10
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents