The AON Diagram Shown Represents a Project

Question 31

Multiple Choice

The AON diagram shown represents a project. If the estimated times for each activity are as shown in the accompanying table, how much slack is there in the completion of Activity 5? The AON diagram shown represents a project. If the estimated times for each activity are as shown in the accompanying table, how much slack is there in the completion of Activity 5?     A) There is no slack, because Activity 5 is on the critical path. B) 1 day C) 2 days D) 3 days E) 4 days The AON diagram shown represents a project. If the estimated times for each activity are as shown in the accompanying table, how much slack is there in the completion of Activity 5?     A) There is no slack, because Activity 5 is on the critical path. B) 1 day C) 2 days D) 3 days E) 4 days


A) There is no slack, because Activity 5 is on the critical path.
B) 1 day
C) 2 days
D) 3 days
E) 4 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents