Solved

Which of the Following Statements Regarding CPM Networks Is TRUE

Question 41

Multiple Choice

Which of the following statements regarding CPM networks is TRUE?


A) There can be multiple critical paths on the same project, all with different durations.
B) The early finish of an activity is the latest early start of all preceding activities.
C) The late start of an activity is its late finish plus its duration.
D) If a specific project has multiple critical paths, all of them will have the same duration.
E) None of these are true.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents