Activity D on a CPM network has predecessors B and C, and has successor F. D has duration 6. B's earliest finish is 18, while C's is 20. F's late start is 26. Which of the following is definitely TRUE?
A) B is a critical activity.
B) C is completed before B.
C) D has no slack but is not critical.
D) D is critical, and has a slack of two days.
E) F is critical, and has zero slack.
Correct Answer:
Verified
Q37: Projects such as road building and plane
Q38: Gantt charts give a timeline for each
Q39: The control of projects involves close monitoring
Q40: Describe the differences between a Gantt chart
Q41: Which of the following statements regarding CPM
Q43: Which of the following statements regarding critical
Q44: The fundamental difference between PERT and CPM
Q45: Slack is the amount of time an
Q46: The network analysis method that allows activity
Q47: A simple CPM network has five activities,
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents