Solved

Activity D on a CPM Network Has Predecessors B and C

Question 42

Multiple Choice

Activity D on a CPM network has predecessors B and C, and has successor F. D has duration 6. B's earliest finish is 18, while C's is 20. F's late start is 26. Which of the following is definitely TRUE?


A) B is a critical activity.
B) C is completed before B.
C) D has no slack but is not critical.
D) D is critical, and has a slack of two days.
E) F is critical, and has zero slack.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents