Which of the following statements regarding critical paths is TRUE?
A) The shortest of all paths through the network is the critical path.
B) Some activities on the critical path may have slack.
C) Every network has only one critical path.
D) On a specific project, there can be multiple critical paths, all with exactly the same duration.
E) The duration of the critical path is the average duration of all paths in the project network.
Correct Answer:
Verified
Q38: Gantt charts give a timeline for each
Q39: The control of projects involves close monitoring
Q40: Describe the differences between a Gantt chart
Q41: Which of the following statements regarding CPM
Q42: Activity D on a CPM network has
Q44: The fundamental difference between PERT and CPM
Q45: Slack is the amount of time an
Q46: The network analysis method that allows activity
Q47: A simple CPM network has five activities,
Q48: Identify, in order, the six steps basic
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents